I have a plethora of events that occur on a single date. Not a "range" as provided for on the basic user interface. Is there a method to change that, rather than a "range" instead allow for a single date?

aeonjess
Mon, 21 Jan 2019 10:47:34 GMT

Hi, You are unable to change the user interface to only display a single date field , however if you events only have one date without having a range, then you can just leave the duration field as 0 (which it is by default when you add a new event) and this will effectively add an event with a single date on the timeline. On the user interface it will just show the same date for both the start date and end date. By default, when you add a new event and change the start date of the event, the end date will also adjust to correspond to the duration, so to add an event with a single date all you need to do is change the start date, and ignore the other fields (as the duration is set to 0 by default) Jess

keithn
Tue, 22 Jan 2019 20:49:31 GMT

Thank you